Case Study
Ravenscraig
Client: Balfour Beatty Civil Engineering
Project: Japanese Knotweed Remediation
Value: Confidential
Duration: 2 weeks
Scope of Works:
- Design of remediation strategy: in-situ remediation
- Liaising with SEPA for review and approval of remediation strategy
- Undertaking of controlled excavations to reduce the volume of arisings
- Pre-treatment of arisings to allow shallow burial
- Implementation of follow up monitoring programme
- Delivery of remediation strategy to successful completion