Case Study
East Plean Primary School
Client: Robertson Construction
Start Date:: April 2012
Completion Date: December 2012
Scope of Works:
We were contracted by Robertson Contruction to install a sprinkler system is to BSEN12845 inc TB221. The system is fed via sprinkler pump and tank through one installation control valve. The work was carried over a six month period from March to September 2012. As a new company, this was our first contract that helped us to gain LPCB approval.